Previous Work
This work was carried out in November 2011 at Mansfield Library.
We were required to insulate all pipework in the building, including pipework in boxings, behind IPS Panels, above ceilings and in the Boiler Room.

The Pipework in the main building was insulated using Phenolic Section and completed with a Foil Faced finish.

The pipework within the Boiler House was insulated with Phenolic Section and finished with Isogenopak.

All pipework and ducting was correctly identified.
Mansfied Library
Home
Thermal & Acoustic Insulation Work, Sheet Metal Work, Removable Insulation Covers & Electric Trace Heating.
About Us
Services
Products
Previous Work
Contact Us
Renal Unit, Kings Mill Hospital
This work was carried out in November 2011, at the Renal Unit, Kings Mill Hospital. We were required to insulate all pipework within the building, including behind IPS and above ceilings. All pipework external to the building also required insulation.


The pipework within the building was insulated using H&V section and was left with a Foil Faced finish.

The pipework underneath the building was Heat Traced, insulated with H&V section and finished with PIB weather proofing.

The pipework to the Air-conditioning Units was insulated using H&V section and completed with PIB weather proofing.

All pipework was correctly identified.